Finding the system and establishing what it is
The first task is to identify the drainage arrangement and locate its main components. Properties without mains drainage may use a septic tank, package sewage treatment plant or sealed cesspit. These systems operate differently, particularly when it comes to discharging treated wastewater.
Inspection covers can become concealed by gardens, gravel, paving or alterations to the property. Drawings and previous drainage records may help locate the installation, but their accuracy needs checking against what is found on site.
A survey should establish and record the following information where it can be verified:
- The type of tank or treatment system and its construction
- Its approximate capacity and the number of chambers
- The location and accessibility of inspection covers
- The inlet and outlet arrangements and visible pipework
- The route and destination of the discharge
- Any pumping equipment or associated electrical controls
Some systems include pump chambers that transfer sewage or treated effluent between parts of the installation. These should be identified because their operation and maintenance requirements form part of the overall condition assessment.
What is checked inside the tank
Internal checks depend on the tank design, access arrangements and whether emptying forms part of the survey. A full tank can prevent a clear view of its structure and internal fittings. Where necessary and appropriate, emptying may be arranged to allow a more detailed examination.
The assessment may include:
- Visible walls, joints and accessible structural components for cracking, displacement or deterioration
- Signs of groundwater entering the tank or wastewater escaping
- The condition of outlet baffles and dip pipes
- Any fitted outlet effluent filter and evidence of blockage or damage
- Inlet and outlet connections, including signs of backing up or surcharging
- Inspection covers, access points and visible defects
Changes in liquid level can indicate a problem, but they do not establish the cause on their own. Groundwater conditions, incoming flows and the tank construction all need consideration. Where leakage is suspected, the report should distinguish the observed evidence from any further testing required.
Assessing the drainage field
The drainage field is an important part of a septic tank installation. Liquid effluent leaving the tank normally passes into a network of underground distribution pipes, allowing further treatment as it moves through suitable ground. A tank may appear sound while the drainage field has problems accepting effluent.
The survey should establish where the discharge goes and identify the drainage field where possible. Relevant observations include saturated ground, standing water, effluent appearing at the surface, signs of previous excavation and unusual wet areas around the suspected drainage route.
These observations help assess the installation, but they are not conclusive tests of drainage field performance. Further investigation may involve examining distribution points, observing how the system responds to flow or assessing the ground conditions. Formal percolation testing is a separate procedure and should not be assumed to form part of every property survey.
The report should explain what was inspected, what evidence was found and which parts of the field could not be assessed. Our information on drainage fields explains their construction and function, while soakaway problems covers common signs of drainage failure. A drainage field for treated sewage effluent is not the same as a surface water soakaway.
Camera inspection of drainage pipework
CCTV drain inspection can help establish the condition of accessible underground pipework between the property and the treatment system. It may reveal displaced joints, cracking, root intrusion, obstructions, standing water or unexpected connections.
Camera inspection is particularly useful where pipe routes are uncertain or where there is evidence of recurring blockages. The footage can support a written description of defects and their locations. Where a formal drain condition coding method is used, the report should identify it.
A camera survey does not automatically establish pipe gradients or prove that a drainage field is working. Some sections may also be inaccessible. The report should identify which runs were inspected and explain any limitations rather than treating the recorded footage as an assessment of the entire installation.
Checking the discharge arrangements and authorisation
Part of a property purchase survey is establishing whether the discharge arrangement is appropriate and what authorisation or supporting records are available. The relevant rules depend on the location of the property, the type of installation and where the effluent discharges.
England
In England, qualifying small sewage discharges may operate under the general binding rules without an environmental permit. A septic tank must not discharge directly into a watercourse. Where an existing septic tank does so, the system must be brought into compliance by connecting to a public sewer, installing a suitable treatment plant or providing a compliant drainage field, as applicable.
Government guidance advises buyers and sellers to agree responsibility for necessary corrective work as a condition of sale. Our septic tank general binding rules page explains the English requirements in more detail.
Scotland
In Scotland, discharges from septic tanks and package treatment plants require authorisation from the Scottish Environment Protection Agency, usually through registration. A survey should identify the discharge arrangement and consider any available SEPA registration or other authorisation records.
Wales and Northern Ireland
In Wales, Natural Resources Wales administers the registration and permitting arrangements for private sewage systems. Many qualifying small discharges require registration rather than an individual permit. In Northern Ireland, discharge consent is administered by the Department of Agriculture, Environment and Rural Affairs. The survey should record the evidence available for the relevant system and jurisdiction.
Useful official guidance includes GOV.UK general binding rules for discharges to ground, GOV.UK general binding rules for discharges to surface water and SEPA guidance on private sewage treatment systems.